Keys Cares About the Environment. Click to learn more about the ways we're Growing Greener Every Day.
Links and Buttons Find us on Facebook! Follow us on Twitter! Watch us on YouTube! Home Power Advantage Sunshine State One Call of Florida
SUBSTATION MAINTENANCE PLANNED; TEMPORARY POWER OUTAGES POSSIBLE

01/30/2009 ~ Keys Energy Services (KEYS) will be performing scheduled substation maintenance on Tuesday, February 3rd and on Thursday, February 5th* from 12:01 – 6:00 a.m. KEYS’ customers should not see an interruption of service during this time, but should be aware the possibility, though remote, of a power outage exists.

To accommodate the planned maintenance work on February 3rd, KEYS’ customers from Key West to Cudjoe Key will be disconnected from the Transmission Line (TIELINE) and powered by local generation at KEYS’ Stock Island Generating Facility. All other KEYS’ customers will remain connected to the TIELINE.

To accommodate planned maintenance work on February 5th, all KEYS’ customers will be disconnected from the TIELINE and powered by local generation at KEYS’ Stock Island Generating Facility.

The planned TIELINE separations will allow for the replacement of equipment at the Big Coppitt and Big Pine Key Electrical Substations.

* The scheduled substation maintenance is contingent on favorable weather conditions.

News Archives: 2018 2017 2016 2015 2014 2013 2012 2011 2010 2009 2008 2007 2006 2005 2004 2003